Technical perspective
Size and scale of the challenge
There are over 600 offshore oil and gas installations in the North Sea, 470
of which are in UK waters. These include sub-sea equipment fixed to the
ocean floor as well as platforms ranging from the smaller structures in the
southern North Sea to the enormous installations of the northern North Sea
built to withstand very harsh weather conditions in deep water. Many were
built in the 1970s and were hailed as technological feats of engineering
when they were installed. The industry now faces the equally challenging
task of decommissioning them.
Fig: Deep water structures can be several hundred metres
high
 Please click on the images below to see a larger view:
One of the main challenges is the many different types and designs of
structure which mean that there is no single tried and tested method for
removal. Most of the structures were designed to suit particular development
and field conditions. They range from small steel lattice-work structures,
through to large heavy concrete or steel structures, and include floating
production, storage and off-loading installations (FPSOs), and under-water
(sub-sea) extraction systems. The following diagrams give some idea of the
diversity of shape and scale.
Fig: A wide variety of structures exist in terms of
overall size and design

The smaller, shallow water installations are themselves large structures by
any standards, often towering to heights of around a hundred
metres,,comparable in size to Big Ben. The enormous concrete or steel
structures which are prolific in deep waters such as those of the northern
North Sea can be as big as the Eiffel Tower and much, much heavier.
Offshore, as well as such installations, there are more than 10,000km of
pipelines, ca. 5000 wells and accumulations of drill cuttings. Associated
with these operations are also 15
onshore terminals.
Fig: ConocoPhillips’s Bacton Terminal

Of the 470 offshore installations present on the UKCS, it is estimated that
10% are floating structures, 30% are sub-sea, 50% are small steel and 10%
are large steel or concrete. Under current regulatory requirements, over 90%
of offshore structures will be completely removed from their marine sites
and brought to shore for re-use, recycling or other disposal means. The
rest, which comprises the very large and heavy steel or concrete
installations (approximately 10 %), will be looked at on an individual basis
to assess whether it is technically feasible (and safe) to remove them,
bearing in mind that there is a general presumption for complete removal. If
they are too difficult or dangerous to be removed to shore, an exceptional
case for “derogation” can be made (see
Legislative Framework)
Decommissioning timescale
It is inherently difficult to predict the exact date of decommissioning for
each structure. There are a number of reasons for this including:
- long term trends in oil and gas prices which determine whether it
remains economic to keep a field in operation;
- long-term certainty on both fiscal and regulatory regimes which will
influence the future investment environment;
- improved production and reservoir recovery methods;
- extending the use of the infrastructure, e.g. for smaller satellite
fields tied-back into existing export systems;
- alternative use of the structures e.g. for gas storage or carbon
sequestration.
The industry is actively pursuing ways to delay decommissioning and
extend the productive life of existing infrastructure, therefore
allowing it to be used to recover the UK’s remaining hydrocarbon
resources to the maximum. This, along with the other timescale
uncertainties, raises another challenge: that of an uncertain market
place for decommissioning in which contractors have a difficulty in
gearing up technology and the workforce requirements for an ever
changing activity plan. The figure below shows the DBERR’s current
estimate of decommissioning dates for the UKCS.
Fig: Estimated Decommissioning Dates – The
decommissioning process is likely to last over 30 years. Source: BERR

Decommissioning cost estimates
As with timing estimates, projections of the overall cost of
decommissioning for the UKCS also vary widely, from around £10bn to
£20bn. Oil & Gas UK’s own activity survey places the cost at just under
£12 billion in real terms. The variables responsible for this range of
estimates include:
- the inclusion/exclusion of wells and pipelines;
- the level of removal i.e. success in achieving derogations for
installations (and final status for pipelines);
- cost estimation methods.
A figurative breakdown of overall UKCS costs is noted in the
figure below:
Fig: Schematic showing an estimated
decommissioning costs breakdown - such estimates are dependent upon
several variables. Source BERR.

Different companies have differing perspectives and methods of
estimating the costs involved in decommissioning projects. The
introduction of cost uncertainty has a negative impact on, for
example, the processes surrounding asset transfer deals, as well as
the market place for the award of decommissioning contracts (see
section 4).
To help standardise decommissioning cost estimation new industry
guidelines on the methodology behind cost assessment have recently
been published by Oil & Gas UK (available free of charge). The aim
is to provide an advisory (as opposed to a prescriptive) service to
ensure an industry wide, comprehensive and uniform approach to
decommissioning cost estimation, as well as improved estimates for
market assessment.
Click to download a free copy of Oil & Gas UK’s
“Guidelines on Decommissioning Cost Estimation”. There is
also an
excel spreadsheet attachment available for download.
The figure below gives a time/cost estimation of the decommissioning
process by UKCS region. It can be noted that the bulk of costs are
likely to be incurred in the deeper waters of the Northern and
Central North Sea.
Fig: Decommissioning costs by region (WoB = West
of Britain, SNS/CNS/NNS = Southern/Central/ Northern North Sea).
Source: Oil & Gas UK / Wood Mackenzie

Offshore infrastructure subject to decommissioning
Fixed platforms
Platforms can be designated as small or large (those in water depths
of more than 100m, with jackets or sub-structures weighing more that
10,000 tonnes).
For small platforms, entire removal to shore is the only option. The
following pictures show a process of decommissioning used in the
southern North Sea, where experience to date runs to more than a
dozen fixed platforms having already been decommissioned, including
all Esmond, Forbes & Gordon field structures and infield platforms
in West Sole, Viking, Leman and Camelot.
Fig: The decommissioning of Southern North Sea
fixed platforms

For the large platforms, the top-sides need to be removed to shore,
but there may be options, under OSPAR 98/3 derogation, for part of
the steel jackets and for concrete substructures.
These include:
- Complete
removal;
- Partial
removal, leaving 55m clear water column for navigational safety.
The cut-off point would be so as to remove as much as reasonably
practical. In the case of North West Hutton, this was at the top
of the “bottle leg” footings (where the thickness of steel meant
that cutting safely with current technology was not possible).
See below.
- Leave in
place, for concrete gravity based structures only, leaving
appropriate navigation aids. The cut-off point is determined by
the construction.
On the UKCS
there are only 40 platforms which qualify to apply for
derogation, 9 concrete and 31 steel. However, not all will take
the derogation option so the total number of structures left on
the sea-bed will be lower (it is unlikely that any new large
platforms will be constructed in the UKCS in the future and all
new structures installed after 1st January 1998 have had to be
capable of total removal).
The first 98/3 derogation approval was for the Ekofisk concrete
tank; the first UKCS derogations were for three Frigg concretes
- two on the UK side approved by UK and one on the Norwegian
side approved by Norway (to
be followed shortly by
MCP01 within the UK sector) and
North
West Hutton. The latter, which received approval from the UK
Government in the first half of 2006 to remove topsides and the
steel jacket down to the bottle-leg footings, is programmed for
decommissioning between 2008 and 2009. It took three years to
consult on the options and final plans will re-cycle or re-use
97% of all materials. There is also a drill cuttings
accumulation around the footings. The figure below illustrates
this.
Fig: Schematic showing the North West Hutton
substructure

Floating and sub-sea
Many of the high profile large structures being decommissioned
in the UK sector have been unusual floating structures. These
include the
Brent Spar,
Maureen and
Hutton TLP installations:
-
Brent Spar - a floating storage and off-loading column,
originally approved (in 1995) for removal to a deep sea bed
disposal site, this was reversed (following direct action by
Greenpeace environmental activists) and in 1999 the
structure was cut into segments to make the base of a ferry
quay in Mekjarik, Norway (see below).
Fig: Brent Spar as it is a) towed to
shore, and b) as part of a new dock construction

-
Maureen – a unique steel gravity base platform (100,000
tonnes), which was floated free from the sea-bed and towed
intact to Norway. Initially full re-use options were
considered, but eventually it too was re-cycled as a quay in
Stord, Norway in 2001. As with Brent Spar, the draft
required deep inshore waters to effect the subsequent
de-construction and disposal. (see below)
Fig: The Maureen installation as it is
a) towed to shore, and b) dismantled

-
Hutton TLP – the first ever Tension Leg Platform (TLP)
which was removed for re-use outside the UK in 2002.
Fig: The Hutton TLP installation being
towed to shore

Recently
there has been an increasing use of sub-sea satellite
developments tied-back to existing fixed platforms, which
makes decommissioning fairly straight forward for those
fields.
Fields with floating systems, especially Floating
Production, Storage and Offloading vessels (FPSOs) tied into
sub-sea manifolds, lend themselves to re-use at the end of
field life. To date floating platform Argyll (1992) and
FPSOs Angus (1993), Emerald (1996), Donan (1998), Blenheim/Bladon
and Durward/Dauntless (both 2000) have been re-used
following field decommissioning.
Fig: An FPSO vessel (with a tanker at
the rear) operating in the Foinaven Field

For more detailed information on past and present North Sea
decommissioning projects, please
click here to be re-directed to the Decommissioning Case
Studies section of the website.
Wells
Fig: a) an FPSO tied into sub-sea
manifolds and b) a sub-sea well tied back to an existing
platform

Following a field Cessation of Production (COP), the
decommissioning of production and injection wells is often
the first phase of the overall programme. On platforms this
requires the removal of conductors from the sea-bed to the
platform deck, which can also have structural implications.
On floating or sub-sea developments, it requires the removal
of sub-sea wellheads to around 5m below the level of the
surrounding sea-bed. After this time it is recommended that
fishermen are commissioned to check the sea-bed for any
remains that could pose a potential hazard for nets and
issue a clearance certificate..
Likewise, the decommissioning of exploration wells is also
an important issue. Companies sometimes choose to plug and
suspend successful exploration wells for future development.
However, there is no record of a well over six years old
being reactivated in such a way, while there are many wells
older than this that have remained suspended. There is a
rigorous tracking of well ownership and location, which is
regularly communicated to fishing vessels to allow on-board
plotters to be updated to help them avoid the hazards. Since
1998, Oil & Gas UK has promoted a campaign for the complete
removal of suspended wells to reduce the sea-bed inventory,
lessen the hazard and maintain a good working relationship
with the fishing industry.
The standards of safety required before wells can be left
are of importance for all these cases. Oil & Gas UK provides
a framework of good industry practice and regulatory
requirements through its Guidelines for the Suspension and
Abandonment of Wells, which is regularly updated to
incorporate recent experience and learning (1995, with
revisions 2001 & 2005). The main issue is to ensure that
effective barriers adequately isolate reservoir fluids both
down hole and at its surface.
Click here to purchase the Oil & Gas UK guidelines on
the “Suspension and Abandonment of Wells”
For more information on suspended wells, please visit the
"Suspended Wells" section of this website.
Pipelines
Fig: Pipeline laying in the North Sea

Pipeline decommissioning involves the pigging, flushing,
filling and plugging of lines, followed by removal or
abandonment in situ. However, the regulations relating to
pipelines are currently controlled by national rather than
international requirements. This, together with a low level
of experience to date, means that the standards required are
difficult to predict.
Pipelines can be laid on top of the sea-bed, trenched or
buried and this may also influence the decommissioning
programme required. In general, if the pipeline is of a
small diameter (less than 12”) it is likely that it will
need to be removed or fully buried. This would apply to all
in-field flow-lines and control bundles. For larger trunk
lines, the options depend on other factors and the
practicality of removal, disposal etc. There are a number of
issues which influence these decisions and will need to be
addressed, including overlapping or crossing pipelines,
concrete mattresses, spans, sea-bed stability etc.
Currently the government recognises that during the course
of field life, pipelines or parts of pipelines may be taken
out of use, at which point operators must give notification
of disuse to the BERR. This can be done via a “disused
pipeline notification” pro forma available for download from
the BERR’s oil and gas website. When this happens, the Secretary of
State has the option of immediately calling for a full
decommissioning programme under the Petroleum Act 1998.
However, this is often not considered the most appropriate
option and it has therefore been agreed that consideration
will be given to handling suitable pipelines under an
informal decommissioning regime (the “Interim
Pipeline Regime”) thereby deferring the full formal
programme until the end of field life.
The Interim Pipeline Regime is intended to ensure that
out-of-use lines do not pose a risk to other users of the
sea or to the environment and that they are covered by an
appropriate surveying and maintenance regime from the point
when they are taken out of use until approval of the formal
decommissioning programme, which is usually at the end of
field life.
Drill cuttings
Fig: Drill cuttings / drilling mud mix

Under some platforms there are large mounds of drill
cuttings, deposited when the wells were drilled. In the main
these only exist in northern North Sea waters, where sea-bed
currents are not strong enough to have dispersed them. These
accumulations also contain drilling mud weighting material
(barite) and hydrocarbons from when oil-based drilling muds
were used. The composition, size and nature vary greatly,
but some piles weigh over 10,000 tonnes, are up to ten
metres high and can extend hundreds of metres from the
platform which they originate from.
There is controversy about what can or should be done with
these accumulations of drill cuttings, giving consideration
to future activities and any ecological implications.
Bio-remediation would take a long time, but bio-availability
of the heavy metal compounds and the hydrocarbons is also
very low.
Several
studies have been undertaken by the industry in response
to OSPAR interest (see OGP,
Oil & Gas UK or OLF
literature and web-sites between 1998 and 2002).
Currently the removal of cuttings accumulations is regulated
as a separate issue from that of the decommissioning of
installations.
OSPAR decision 2006/5 on the management regime for
cuttings piles, stipulates that operators must survey any
drill cuttings accumulations which are known to contain
organic (oil based) drilling mud. If the result demonstrates
that the concentration of organic drilling fluids exceeds
certain thresholds, operators must then consider which
disposal option is best suited for the particular cuttings
pile. Options include: removal of the cuttings through
down-hole injection, or via ship-to-shore transfer for
processing or disposal; covering the pile with a protective
layer and allowing the cuttings to biodegrade in situ; or,
initiate a biological remediation scheme to catalyse
bio-degradation of the cuttings.
The general consensus at this time is that they should be
assessed on a case-by-case basis. Consideration may be given
to the following:
- In
situ, without treatment or capped using sand, gravel,
concrete or aggregate/rocks. Some level of monitoring
and/or maintenance might also be expected. There is also
the possibility of introducing bacteria to accelerate
bio-remediation. In the past, sea-bed dispersal has also
been used, but it is unlikely that this would be
acceptable in the future.
-
Removal by pumping or dredging, with subsequent disposal
by re-injection into a disposal well or into landfill.
Platform footings may constrain access and handling of
the materials can also be impractical. Also, the lifting
of cuttings is likely, by dispersal, to broaden any
onsite environmental impact and subsequent disposal,
because of the sea water dilution effect, tends to
magnify the problem.
For
more detailed information on this topic please see the
specific
“drill cuttings” section of the website.
Debris
Once the main structures have been removed, there may
remain small items of debris on the sea bed which has
fallen overboard during the decommissioning process or
at some point during the lifetime of the installation.
Examples include scaffolding, cables, concrete blocks
etc. These remains must also be entirely removed or
protected and monitored. A comprehensive survey of the
site should be carried out – usually in the presence of
an independent organisation, very often the fishermen.
Any materials which have been left behind can then be
picked up and disposed of onshore, at which point a
certificate can be issued to confirm that the sea bed
has been fully and comprehensively “cleaned” of any oil
and gas related debris.
The aim of the post-decommissioning activity is to
ensure anything left behind does not adversely affect
the marine environment or other users of the sea (e.g.
fishermen, shipping). |