Oil & Gas UK

Decommissioning Index Decommissioning Index Next Section Next

Technical perspective

Size and scale of the challenge

There are over 600 offshore oil and gas installations in the North Sea, 470 of which are in UK waters. These include sub-sea equipment fixed to the ocean floor as well as platforms ranging from the smaller structures in the southern North Sea to the enormous installations of the northern North Sea built to withstand very harsh weather conditions in deep water. Many were built in the 1970s and were hailed as technological feats of engineering when they were installed. The industry now faces the equally challenging task of decommissioning them.

Fig: Deep water structures can be several hundred metres high

Please click on the images below to see a larger view:

One of the main challenges is the many different types and designs of structure which mean that there is no single tried and tested method for removal. Most of the structures were designed to suit particular development and field conditions. They range from small steel lattice-work structures, through to large heavy concrete or steel structures, and include floating production, storage and off-loading installations (FPSOs), and under-water (sub-sea) extraction systems. The following diagrams give some idea of the diversity of shape and scale.

Fig: A wide variety of structures exist in terms of overall size and design



The smaller, shallow water installations are themselves large structures by any standards, often towering to heights of around a hundred metres,,comparable in size to Big Ben. The enormous concrete or steel structures which are prolific in deep waters such as those of the northern North Sea can be as big as the Eiffel Tower and much, much heavier.

Offshore, as well as such installations, there are more than 10,000km of pipelines, ca. 5000 wells and accumulations of drill cuttings. Associated with these operations are also 15 onshore terminals.

Fig: ConocoPhillips’s Bacton Terminal


Of the 470 offshore installations present on the UKCS, it is estimated that 10% are floating structures, 30% are sub-sea, 50% are small steel and 10% are large steel or concrete. Under current regulatory requirements, over 90% of offshore structures will be completely removed from their marine sites and brought to shore for re-use, recycling or other disposal means. The rest, which comprises the very large and heavy steel or concrete installations (approximately 10 %), will be looked at on an individual basis to assess whether it is technically feasible (and safe) to remove them, bearing in mind that there is a general presumption for complete removal. If they are too difficult or dangerous to be removed to shore, an exceptional case for “derogation” can be made (see Legislative Framework)


Decommissioning timescale

It is inherently difficult to predict the exact date of decommissioning for each structure. There are a number of reasons for this including:

  • long term trends in oil and gas prices which determine whether it remains economic to keep a field in operation;
  • long-term certainty on both fiscal and regulatory regimes which will influence the future investment environment;
  • improved production and reservoir recovery methods;
  • extending the use of the infrastructure, e.g. for smaller satellite fields tied-back into existing export systems;
  • alternative use of the structures e.g. for gas storage or carbon sequestration.

The industry is actively pursuing ways to delay decommissioning and extend the productive life of existing infrastructure, therefore allowing it to be used to recover the UK’s remaining hydrocarbon resources to the maximum. This, along with the other timescale uncertainties, raises another challenge: that of an uncertain market place for decommissioning in which contractors have a difficulty in gearing up technology and the workforce requirements for an ever changing activity plan. The figure below shows the DBERR’s current estimate of decommissioning dates for the UKCS.

Fig: Estimated Decommissioning Dates – The decommissioning process is likely to last over 30 years. Source: BERR


 

Decommissioning cost estimates

As with timing estimates, projections of the overall cost of decommissioning for the UKCS also vary widely, from around £10bn to £20bn. Oil & Gas UK’s own activity survey places the cost at just under £12 billion in real terms. The variables responsible for this range of estimates include:

  • the inclusion/exclusion of wells and pipelines;
  • the level of removal i.e. success in achieving derogations for installations (and final status for pipelines);
  • cost estimation methods.

A figurative breakdown of overall UKCS costs is noted in the figure below:

Fig: Schematic showing an estimated decommissioning costs breakdown - such estimates are dependent upon several variables. Source BERR.



Different companies have differing perspectives and methods of estimating the costs involved in decommissioning projects. The introduction of cost uncertainty has a negative impact on, for example, the processes surrounding asset transfer deals, as well as the market place for the award of decommissioning contracts (see section 4).

To help standardise decommissioning cost estimation new industry guidelines on the methodology behind cost assessment have recently been published by Oil & Gas UK (available free of charge). The aim is to provide an advisory (as opposed to a prescriptive) service to ensure an industry wide, comprehensive and uniform approach to decommissioning cost estimation, as well as improved estimates for market assessment.

Click to download a free copy of Oil & Gas UK’s “Guidelines on Decommissioning Cost Estimation”. There is also an excel spreadsheet attachment available for download.

The figure below gives a time/cost estimation of the decommissioning process by UKCS region. It can be noted that the bulk of costs are likely to be incurred in the deeper waters of the Northern and Central North Sea.

Fig: Decommissioning costs by region (WoB = West of Britain, SNS/CNS/NNS = Southern/Central/ Northern North Sea). Source: Oil & Gas UK / Wood Mackenzie



Offshore infrastructure subject to decommissioning


Fixed platforms

Platforms can be designated as small or large (those in water depths of more than 100m, with jackets or sub-structures weighing more that 10,000 tonnes).

For small platforms, entire removal to shore is the only option. The following pictures show a process of decommissioning used in the southern North Sea, where experience to date runs to more than a dozen fixed platforms having already been decommissioned, including all Esmond, Forbes & Gordon field structures and infield platforms in West Sole, Viking, Leman and Camelot.

Fig: The decommissioning of Southern North Sea fixed platforms



For the large platforms, the top-sides need to be removed to shore, but there may be options, under OSPAR 98/3 derogation, for part of the steel jackets and for concrete substructures.

These include:

  • Complete removal;
  • Partial removal, leaving 55m clear water column for navigational safety. The cut-off point would be so as to remove as much as reasonably practical. In the case of North West Hutton, this was at the top of the “bottle leg” footings (where the thickness of steel meant that cutting safely with current technology was not possible). See below.
  • Leave in place, for concrete gravity based structures only, leaving appropriate navigation aids. The cut-off point is determined by the construction.

On the UKCS there are only 40 platforms which qualify to apply for derogation, 9 concrete and 31 steel. However, not all will take the derogation option so the total number of structures left on the sea-bed will be lower (it is unlikely that any new large platforms will be constructed in the UKCS in the future and all new structures installed after 1st January 1998 have had to be capable of total removal).

The first 98/3 derogation approval was for the Ekofisk concrete tank; the first UKCS derogations were for three Frigg concretes - two on the UK side approved by UK and one on the Norwegian side approved by Norway (to be followed shortly by MCP01 within the UK sector) and North West Hutton. The latter, which received approval from the UK Government in the first half of 2006 to remove topsides and the steel jacket down to the bottle-leg footings, is programmed for decommissioning between 2008 and 2009. It took three years to consult on the options and final plans will re-cycle or re-use 97% of all materials. There is also a drill cuttings accumulation around the footings. The figure below illustrates this.

Fig: Schematic showing the North West Hutton substructure



Floating and sub-sea

Many of the high profile large structures being decommissioned in the UK sector have been unusual floating structures. These include the Brent Spar, Maureen and Hutton TLP installations:

  • Brent Spar - a floating storage and off-loading column, originally approved (in 1995) for removal to a deep sea bed disposal site, this was reversed (following direct action by Greenpeace environmental activists) and in 1999 the structure was cut into segments to make the base of a ferry quay in Mekjarik, Norway (see below).

    Fig: Brent Spar as it is a) towed to shore, and b) as part of a new dock construction


     
  • Maureen – a unique steel gravity base platform (100,000 tonnes), which was floated free from the sea-bed and towed intact to Norway. Initially full re-use options were considered, but eventually it too was re-cycled as a quay in Stord, Norway in 2001. As with Brent Spar, the draft required deep inshore waters to effect the subsequent de-construction and disposal. (see below)

    Fig: The Maureen installation as it is a) towed to shore, and b) dismantled



     
  • Hutton TLP – the first ever Tension Leg Platform (TLP) which was removed for re-use outside the UK in 2002.

    Fig: The Hutton TLP installation being towed to shore


     

Recently there has been an increasing use of sub-sea satellite developments tied-back to existing fixed platforms, which makes decommissioning fairly straight forward for those fields.
Fields with floating systems, especially Floating Production, Storage and Offloading vessels (FPSOs) tied into sub-sea manifolds, lend themselves to re-use at the end of field life. To date floating platform Argyll (1992) and FPSOs Angus (1993), Emerald (1996), Donan (1998), Blenheim/Bladon and Durward/Dauntless (both 2000) have been re-used following field decommissioning.

Fig: An FPSO vessel (with a tanker at the rear) operating in the Foinaven Field


For more detailed information on past and present North Sea decommissioning projects, please click here to be re-directed to the Decommissioning Case Studies section of the website.


Wells

Fig: a) an FPSO tied into sub-sea manifolds and b) a sub-sea well tied back to an existing platform



Following a field Cessation of Production (COP), the decommissioning of production and injection wells is often the first phase of the overall programme. On platforms this requires the removal of conductors from the sea-bed to the platform deck, which can also have structural implications. On floating or sub-sea developments, it requires the removal of sub-sea wellheads to around 5m below the level of the surrounding sea-bed. After this time it is recommended that fishermen are commissioned to check the sea-bed for any remains that could pose a potential hazard for nets and issue a clearance certificate..

Likewise, the decommissioning of exploration wells is also an important issue. Companies sometimes choose to plug and suspend successful exploration wells for future development. However, there is no record of a well over six years old being reactivated in such a way, while there are many wells older than this that have remained suspended. There is a rigorous tracking of well ownership and location, which is regularly communicated to fishing vessels to allow on-board plotters to be updated to help them avoid the hazards. Since 1998, Oil & Gas UK has promoted a campaign for the complete removal of suspended wells to reduce the sea-bed inventory, lessen the hazard and maintain a good working relationship with the fishing industry.

The standards of safety required before wells can be left are of importance for all these cases. Oil & Gas UK provides a framework of good industry practice and regulatory requirements through its Guidelines for the Suspension and Abandonment of Wells, which is regularly updated to incorporate recent experience and learning (1995, with revisions 2001 & 2005). The main issue is to ensure that effective barriers adequately isolate reservoir fluids both down hole and at its surface.

Click here to purchase the Oil & Gas UK guidelines on the “Suspension and Abandonment of Wells

For more information on suspended wells, please visit the "Suspended Wells" section of this website.


Pipelines

Fig: Pipeline laying in the North Sea



Pipeline decommissioning involves the pigging, flushing, filling and plugging of lines, followed by removal or abandonment in situ. However, the regulations relating to pipelines are currently controlled by national rather than international requirements. This, together with a low level of experience to date, means that the standards required are difficult to predict.

Pipelines can be laid on top of the sea-bed, trenched or buried and this may also influence the decommissioning programme required. In general, if the pipeline is of a small diameter (less than 12”) it is likely that it will need to be removed or fully buried. This would apply to all in-field flow-lines and control bundles. For larger trunk lines, the options depend on other factors and the practicality of removal, disposal etc. There are a number of issues which influence these decisions and will need to be addressed, including overlapping or crossing pipelines, concrete mattresses, spans, sea-bed stability etc.

Currently the government recognises that during the course of field life, pipelines or parts of pipelines may be taken out of use, at which point operators must give notification of disuse to the BERR. This can be done via a “disused pipeline notification” pro forma available for download from the BERR’s oil and gas website. When this happens, the Secretary of State has the option of immediately calling for a full decommissioning programme under the Petroleum Act 1998. However, this is often not considered the most appropriate option and it has therefore been agreed that consideration will be given to handling suitable pipelines under an informal decommissioning regime (the “Interim Pipeline Regime”) thereby deferring the full formal programme until the end of field life.

The Interim Pipeline Regime is intended to ensure that out-of-use lines do not pose a risk to other users of the sea or to the environment and that they are covered by an appropriate surveying and maintenance regime from the point when they are taken out of use until approval of the formal decommissioning programme, which is usually at the end of field life.


Drill cuttings

Fig: Drill cuttings / drilling mud mix



Under some platforms there are large mounds of drill cuttings, deposited when the wells were drilled. In the main these only exist in northern North Sea waters, where sea-bed currents are not strong enough to have dispersed them. These accumulations also contain drilling mud weighting material (barite) and hydrocarbons from when oil-based drilling muds were used. The composition, size and nature vary greatly, but some piles weigh over 10,000 tonnes, are up to ten metres high and can extend hundreds of metres from the platform which they originate from.

There is controversy about what can or should be done with these accumulations of drill cuttings, giving consideration to future activities and any ecological implications. Bio-remediation would take a long time, but bio-availability of the heavy metal compounds and the hydrocarbons is also very low.

Several studies have been undertaken by the industry in response to OSPAR interest (see OGP, Oil & Gas UK or OLF literature and web-sites between 1998 and 2002).

Currently the removal of cuttings accumulations is regulated as a separate issue from that of the decommissioning of installations. OSPAR decision 2006/5 on the management regime for cuttings piles, stipulates that operators must survey any drill cuttings accumulations which are known to contain organic (oil based) drilling mud. If the result demonstrates that the concentration of organic drilling fluids exceeds certain thresholds, operators must then consider which disposal option is best suited for the particular cuttings pile. Options include: removal of the cuttings through down-hole injection, or via ship-to-shore transfer for processing or disposal; covering the pile with a protective layer and allowing the cuttings to biodegrade in situ; or, initiate a biological remediation scheme to catalyse bio-degradation of the cuttings.

The general consensus at this time is that they should be assessed on a case-by-case basis. Consideration may be given to the following:

  • In situ, without treatment or capped using sand, gravel, concrete or aggregate/rocks. Some level of monitoring and/or maintenance might also be expected. There is also the possibility of introducing bacteria to accelerate bio-remediation. In the past, sea-bed dispersal has also been used, but it is unlikely that this would be acceptable in the future.
  • Removal by pumping or dredging, with subsequent disposal by re-injection into a disposal well or into landfill. Platform footings may constrain access and handling of the materials can also be impractical. Also, the lifting of cuttings is likely, by dispersal, to broaden any onsite environmental impact and subsequent disposal, because of the sea water dilution effect, tends to magnify the problem.

For more detailed information on this topic please see the specific “drill cuttings” section of the website.
 

Debris

Once the main structures have been removed, there may remain small items of debris on the sea bed which has fallen overboard during the decommissioning process or at some point during the lifetime of the installation. Examples include scaffolding, cables, concrete blocks etc. These remains must also be entirely removed or protected and monitored. A comprehensive survey of the site should be carried out – usually in the presence of an independent organisation, very often the fishermen. Any materials which have been left behind can then be picked up and disposed of onshore, at which point a certificate can be issued to confirm that the sea bed has been fully and comprehensively “cleaned” of any oil and gas related debris.

The aim of the post-decommissioning activity is to ensure anything left behind does not adversely affect the marine environment or other users of the sea (e.g. fishermen, shipping).

Decommissioning Index Decommissioning Index Next Section Next

© 2008 The United Kingdom Offshore Oil and Gas Industry Association trading as Oil & Gas UK
Registered Office: 2nd Floor, 232-242 Vauxhall Bridge Road, London, SW1V 1AU
Company No: 1119804
London: Tel 020 7802 2400  Fax 020 7802 2401    Aberdeen: Tel 01224 577 250  Fax 01224 577 251
Email info@oilandgasuk.co.uk  Web http://www.oilandgasuk.co.uk/

Legal and Copyright Issues and Privacy Statement