Project management, engineering and safety
General
One of the challenges concerning decommissioning is that most North Sea
structures were custom built for the particular field conditions, so
decommissioning solutions will be equally as varied, with no readily tried and
tested techniques. The work is non-productive so a key objective will be to find
ways to reduce costs. The possibilities of aggregating work over several
structures or scheduling it to coincide with slack time, with flexible
deadlines, have been mooted as possible strategies. Developing new techniques or
vessels to improve capabilities beyond straight de-construction
reverse-engineering processes may also raise possibilities.
However, with the continual change in field cessation of production (COP) and
decommissioning timings, it is difficult for contractors/suppliers to understand
and react to market signals. A key part of the way forward for industry
therefore is to be more lucid on its future operational plans so the supply
chain can respond more effectively.
Issues which should be considered in the decommissioning programme include:
- Well killing, plugging, abandoning and surface structure removal
operations: this, can take place before the formal process
decommissioning programme is complete;
- Clean-up, preparation and removal of top-sides: hydrocarbons have to
be removed and systems isolated, purged and cleaned before removal;
- Steel jacket removal: many deep water structures were floated in
place, not lifted with a crane-barge, and so may have to be removed in
sections;
- In-field flow-line removal: especially difficult if adjacent fields
are still producing;
- Clearance of all debris on the sea-bed..
These processes will involve a great many hazards which will need to
be safely managed during the decommissioning programme implementation.
These may include:
- Use of explosives, for under-water cutting: giving consideration
to possible collateral damage to structures and their stability,
divers, marine mammals or floating vessels;
- Ageing and corroding structures: suitability for decommissioning
operations, un-planned eventualities arising from
old/poor/incomplete records etc;
- Dealing with contaminants: this needs careful consideration,
especially for low specific activity (LSA) scale, poly-chlorinated
biphenyls, PCBs, asbestos etc.;
- Lifting operations: especially heavy-lift or through water/air
interface;
- Marine vessel interactions and sea-state/weather conditions;
- Personnel travel (helicopters) and accommodation/ maintenance of
life-support on ‘dead’ platforms
Criteria to be considered in determining a solution
The DECC guidelines state that the criteria used to determine the
most appropriate decommissioning solutions needs to take into
account:
- Local and
international regulations;
- Impacts on
the marine environment and other users of that environment;
- Re-use and
re-cycling opportunities;
- Cost,
safety and the practical availability of technology.
Environment: when considering the environmental impacts of a
given option it is necessary to assess the wider effects on the
land, sea and air of the energy used, the emissions, discharges
and waste streams generated and the effects they have on the
marine flora, fauna and other users of the sea.
Re-use, recycling and disposal: Apart from FPSOs, the
re-use of platforms or even process equipment has been
non-existent to date. The reasons why this does not make
economic sense in the North Sea include the lack of operational
confidence in second-hand equipment in a high cost environment,
re-certification issues, tax and/or duty anomalies and
customisation mismatch. A more likely possibility exists of
refurbishment and re-use in other areas of the world ,e.g.
Hutton TLP in Russia, or for some other purpose, e.g. Brent Spar
and Maureen which were cut up to build quays. Failing that, most
are brought to shore and re-cycled as scrap. There is always a
proportion that will end as landfill, but this should be reduced
to as low as practical and is usually less than 10% by weight.
Cost & safety: it is the operator’s responsibility to
find the most cost-effective option which doesn’t compromise the
safety of workers or the environment. At present, the cost for
platforms is in the order of £30million for a small platform in
the southern North Sea, and £100-200million for medium to large
sized platforms in the northern sector.
Public opinion: the views and concerns of people outside
the industry are important, not just overall for setting the
legislative climate but also individually, through statutory and
other consultees influencing regulatory approvals (see 4.2
below).
Technology: New offshore technologies are continually
being developed, evaluated and tested in order to ensure that
the best technology is available to provide safe and efficient
procedures. To date most decommissioning programmes have relied
upon heavy-lift vessels which are designed to take the structure
apart offshore piece by piece.
Research and
development
Research and development (R&D) is carried out across the
industry by operators, major contractors, specialist suppliers
and universities sometimes through programmes supported by
government. R&D areas to date include the following:
-
Alternative removal methods, looking to develop new vessels
attempting to remove top-sides in one go or in the floating
removal of jackets;
-
Underwater cutting. There have been a lot of advances here
through the use of abrasive water-jets, diamond wire cutters
and shaped explosive charges;
- Drill
cuttings removal;
-
Lifting, back-loading and sea-fastening methods.
Fig: A diamond wire cutter – severing a
steel platform leg

Clearly different technologies will be needed dependent upon
the type and location of structure to be decommissioned.
Technological research and development is also being
conducted to assist with the re-commissioning of some
structures for potential re-use, the recycling of unwanted
scrap materials, and the orderly and efficient disposal and
treatment of wastes onshore.
Last updated 14th May 2009 |