Legislative framework
International legislation
The process of decommissioning is very strictly regulated by international,
regional and national legislation. These regulate both the removal of
installations (primarily concerned with safely of navigation and other users of
the sea) and disposal (primarily aimed at pollution prevention). There is a
framework of international conventions which, in turn, influence national
legislative requirements. The primary ones are noted below:
- UNCLOS: The United Nations Convention on the Law of the Seas,
1982 (UNCLOS), superseded the 1958 Geneva Convention and Article 60 (3)
permits the partial removal of structures provided that IMO criteria are
met. This first came into force in 1994 and was ratified by the UK in
1997.
- London(Dumping)Convention: The 1972 London Convention (and
the subsequent 1996 Protocol) made the provision of generic guidance for
any wastes that can be dumped at sea. New guidelines were adopted in
2000, to specify different classes of waste, including platforms and
other man-made waste.
- IMO: The International Maritime Organisation (IMO),
headquartered in London, sets the standards and guidelines for the
removal of offshore installations worldwide. The 1989 IMO Guidelines
require the complete removal of all structures in water depths less than
100m and weighing less than 4000 tonnes. Those in deeper waters can be
partially removed, leaving a minimum 55m of clear water for the safety
of navigation. All structures installed after 1st January 1998 must be
designed so as to be feasible for complete removal. Many of these IMO
guidelines are superseded by OSPAR 98/3, but some remain relevant:
- any disused installation, structure or part thereof, which
projects above the sea (i.e. the topsides) should be adequately
maintained;
- an unobstructed water column of at least 55m must be provided
above the remains of any partially removed installation to ensure
safety of navigation;
- the position, surveyed depth and dimensions of any installation
not entirely removed should be indicated on nautical charts and any
remains, where necessary, properly marked with aids to navigation;
- the person responsible for maintaining the aids to navigation and
for monitoring the condition of any remaining material should be
identified;
- it should be clear where liability lies for meeting any future
claims for damages.
- OSPAR: In 1992 the Oslo and Paris Convention for the
Protection of the Marine Environment of the North East Atlantic (OSPAR)
was drawn up to replace the 1972 Oslo Convention on dumping from
ships and the 1974 Paris Convention on discharges from land. There
are 16 contracting parties, including the UK. Until June 1995, the
OSPAR Convention permitted, under certain circumstances, the
disposal at sea of parts or all of disused offshore installations;
but this changed after the Brent Spar affair.
In July 1998, at the OSPAR Ministerial meeting in Sintra, Portugal a
new regulatory framework was drawn up which no longer permits
disposal of offshore structures at sea (except for exceptional
circumstances). Decision 98/3 came into force in February 1999 and
requires:
- The topsides of all installations to be removed to shore;
- All sub-structures or jackets weighing less than 10,000 tonnes to
be completely removed to shore for reuse, recycle or disposal on
land;
However, in addition to these stipulations the legislation
provides, on a case-by-case basis, a mechanism of derogation where
there may be practical difficulty in removing installations, i.e.
the footings of large steel platforms weighing over 10,000 tonnes,
the concrete gravity based platform sub-structures, or concrete
anchor bases and other structures with significant damage or
deterioration (which would prevent removal).
The decision for granting derogation ultimately lies with the UK
government, following technological justification and appropriate
consultation with other OSPAR Contracting Parties. These rules are
enshrined in UK legislation through the Petroleum Act 1998 (but do
not apply to pipelines). Every three years after 1999, in light of
the experience of relevant research and the exchange of information,
the OSPAR Commission reviews the criteria for future derogations.
However, this was not changed in 2002 or 2005. The next review is
planned for 2008.
UK regulations and due process
The
Petroleum Act 1998 regulates decommissioning of oil and gas
installations and pipelines on the UKCS. Under the 1998 Act (which
superseded the 1989 Petroleum Act) a decommissioning programme
should contain an estimate of the cost of the measures proposed,
specify the times within which those measures are to be taken and,
where an installation or pipeline is to remain in position or be
only partly removed, include provision for maintenance where
necessary. It is recognised that, where appropriate, a
decommissioning programme will deal with both removal and disposal
of an installation or pipeline.
Under the act the relevant parties (operators and owners, as
designated by the BERR through serving Section 29 Notices) are
joint and severally responsible for submitting an appropriate
decommissioning programme to the Secretary of State within a
specified time frame. Section 34 of the Petroleum Act also
stipulates that the BERR can recall any previous owner of the
installation to be responsible for the costs associated with the
decommissioning programme.
These programmes are available for public scrutiny and undertake a
period of consultation to receive (and address) comments from other
government departments/agencies, statutory consultees (i.e. fishing
organisations, non-governmental organisations, members of the public
and other bodies). Prior to submission, operators (on behalf of
joint-venture owners) will need to undertake studies, verification
inspections and option assessments to include as justification for
the proposed decommissioning programme. It then passes through the
stages detailed in the next section.
The industry and DTI commissioned the Policy Studies
Institute, PSI, to develop a methodology that applied sustainable
development principles to this options assessment process. The resultant
report can be viewed at
http://www.psi.org.uk/docs/2005/UKOOA/Decommissioning-working%20paper.pdf
The decommissioning programme approval process
The BERR
Guidance Notes for Industry – “Decommissioning of Offshore
Installations and Pipelines under the Petroleum Act 1998”, provides
a guide to the decommissioning process, and has recently been
revised to include the process for derogation application under
OSPAR 98/3.
The Introduction provides a simplistic description of the
main stages involved in the implementation of a decommissioning
project. A more complete breakdown of the procedure is described
below. Six main stages to the process can be identified:
Fig: The six main stages in the decommissioning
process. Souce: BERR decommissioning guidance notes for Industry

The flow diagram below summarises these stages; in addition the
timing of activities related to OSPAR derogations cases are
included.
Fig: A breakdown of a typical UKCS
Decommissioning Process

Stage 3, “consultations with interested parties and the public” is
covered more fully under the section
"Commercial perspective"
In addition, the
Oil & Gas UK environmental legislation website
provides a detailed breakdown of the consents required and actions
arising at each stage of the decommissioning process for
installations and pipelines, as well as for well suspension and
abandonment.
The BERR guidance notes state that a programme may deal with the
decommissioning of all of the facilities located on a field or part
of the facilities, including a single installation or pipeline. The
precise content of a programme may vary according to the
circumstances. However, the following sections are likely to be
necessary in most cases:
-
Introduction
- Executive
summary
- Background
information
- Description
of items to be decommissioned
- Inventory
of materials
- Removal and
disposal options
- Selected
removal and disposal option
- Wells
- Drill
cuttings
-
Environmental Impact Assessment (EIA)
- Interested
party consultations
- Costs
- Schedule
- Project
management and verification
- Debris
clearance
- Pre- and
post-decommissioning monitoring and maintenance
- Supporting
studies
In addition,
to approve a decommissioning programme, the following will also
need to be obtained as appropriate:
-
Confirmation that the requirements of the Coast Protection
Act 1949 have been satisfied;
-
Acceptance of an Abandonment Safety Case under the Offshore
Installations (Safety Case) Regulations 2005 (installations
only);
-
Fulfilment of notification requirements to Health and Safety
Executive (HSE) under regulation 22 of the Pipeline Safety
Regulations 1996;
- Any
environmental consents or permits required during
decommissioning activity; including Parts I and II of the
Food and Environmental Protection Act 1985;
-
Approvals for the trans-boundary shipment of waste,
including authorisation under the Radioactive Substances Act
1993, and;
-
Approval of a well abandonment programme in accordance with
the obligation contained in the petroleum production
licence.
Where
appropriate, consideration of the draft decommissioning
programme will run in parallel with:
-
Consideration by BERR Licensing and Consent Unit Field
Teams of any Cessation of Production (COP) document (the
procedures for submitting an application for COP are set
out in the BERR's ‘Guidance Notes on Procedures for
Regulating Offshore Oil and Gas Field Developments’
which can be viewed on the
BERR's Oil & Gas Website);
-
Consideration by the HSE of the Abandonment Safety Case;
-
Consideration of any environmental permits or consents,
and;
- any
onshore disposal consents or licences which may be
necessary, including any trans-frontier shipment of
waste issues;
The
following approach will be taken in considering the
decommissioning of pipelines on the UKCS:
-
Decisions will be taken in the light of individual
circumstances;
-
The
potential for reuse of the pipeline in connection
with further hydrocarbon developments should be
considered before decommissioning together with
other existing projects (such as hydrocarbon
storage). If reuse is considered viable, suitable
and sufficient maintenance of the pipeline must be
detailed;
-
All
feasible decommissioning options should be
considered and a comparative assessment made;
-
Any
removal or partial removal of a pipeline should be
performed in such a way as to cause no significant
adverse effects upon the marine environment;
-
Any
decision to leave a pipeline in place should have
regard to the likely deterioration of the material
involved and its present and possible future effect
on the marine environment;
-
Account should be taken of other users of the sea.
|