Case Studies
The following section provides information on some past and present
decommissioning projects in the North Sea.
Fig: Approximate locations of the North Sea
decommissioning projects detailed in this section

North West Hutton
Fig: a) A schematic view of the entire NW Hutton
structure, and b) an aerial view of the topsides

North West Hutton is a large steel platform installed in 1981 comprising
drilling, production and accommodation facilities. It was operated by Amoco
(U.K.) Exploration Company (now a subsidiary of BP plc.) and is located in
the Northern North Sea (block number 211/27a) in a water depth of 143 m. The
total topsides weight is around 20 000 tonnes. The jacket consists of an 8
leg, X-braced steel space frame fixed to the sea bed. The total jacket
weight is 17 500 tonnes including the weight of the piles.
North West Hutton ceased production in July 2002 and since July 2004 has
been classified as a “normally unattended installation” whilst the removal
and disposal options are prepared. The installation is regularly visited to
inspect the structure and perform maintenance duties on essential equipment.
The decommissioning programme for the installation was approved in April
2006 by the then DTI. The programme requires that: the topsides and steel
jacket down to the top of the footings (the base of the jacket) are
completely removed for recycling onshore; the jacket footings are to be left
in place, including the piles which fix the structure to the seabed (under
an OSPAR derogations ruling); the drill cuttings pile will be left in place
to allow the seabed to recover naturally; the oil pipeline to be trenched
and buried and the gas pipeline, which is already trenched, will be left in
place.
The final programme is based on a comprehensive assessment of all options
involving a range of external studies. These investigated the key safety,
environmental, social, technical and economic aspects of various
decommissioning solutions. An Independent Review Group of six environmental
experts and engineers from the UK, Norway and Germany verified that the
assessment process and studies were comprehensive and objective. A
stakeholder consultation process gathered views from a wide range of
organisations and individuals and these were taken into consideration in
arriving at the programme recommendations. The statutory public consultation
on the proposals was completed in March 2005. Consultation on the jacket
proposals via the OSPAR process was completed in December 2005.
The contract for the removal and onshore disposal and recycling of the
installation was awarded to Heerema Marine Contractors in September 2006.
Offshore removal work is expected to start in 2008 and be completed by the
end of 2009. The topsides and jacket will be removed by heavy lift vessel
and taken to the Able yard on Teesside, where it is estimated that 97 % of
the material recovered will be recycled.
Click here for more detailed information on the decommissioning of North
West Hutton from the BP website.
Hutton TLP
Fig: The Hutton TLP after being floated away from it’s
position on the Hutton Field

Hutton TLP was the first ever production Tension Leg Platform (TLP) – a
floating production platform permanently moored to the sea floor via tethers
or tendons (tension legs) at each of the structures corners. Hutton TLP was
originally installed in 1984 by Conoco, but at the time of decommissioning
it had been bought by Kerr-McGee. It was removed for re-use outside the UK
when the platform was purchased by Seymorneftegaz in August 2002, and after
having its decommissioning programme accepted by the UK Government. The
floating platform was towed to Murmansk in Russia where the topsides
facilities and main hull were de-mated. Subsequently the topsides were
transported by barge to the Sevmash fabrication yard at Severodvinsk, where
they were temporarily stored while undergoing refurbishment and refitting.
After completion the topsides were reinstalled onto a new hull structure,
and towed into position ready for a new role in the development of the
Prirazlomnoye Field, 1200 km north east of Arkhangelsk in the Barents Sea.
Brent Spar
Fig: a) Aerial view of the Brent Spar installation. b)
Brent Spar with Greenpeace protestors

The Brent Spar was taken out of operation in 1991 after some 15 years'
service in the
Shell/Esso Brent field in the Northern North Sea - the UK's largest
source of oil and gas. A very large floating oil storage and loading buoy,
the Spar had stored oil from the Brent "A" platform and acted as a tanker
loading facility for the whole of the Brent field.
Detailed studies by several independent companies established that deepwater
disposal of the Spar at a site in the deep Northern Atlantic was the Best
Practicable Environmental Option (BPEO). The UK Government publicly approved
this original plan in February 1995, and also informed the European Union
and the twelve countries in continental Europe who were signed up to the
Oslo Convention for the protection of the marine environment.
However, these scientific and risk evaluations were largely swept aside in
the exceptional events of the summer of 1995, when outrage against deepwater
disposal of the Spar arose in many people from a deeply-rooted belief in the
principle of "clean seas". Shell abandoned the deepwater disposal plan on
20th June. The UK Government accepted this course of action and helped Shell
to obtain a licence from the Norwegian authorities allowing the Spar to be
anchored in the deep waters of Erfjord. A series of stakeholder dialogue
seminars were held across Europe to help find a publicly acceptable solution
for the Brent Spar.
Following a long and detailed evaluation of contractor bids, in January 1998
Shell announced its choice of solution for Spar - a "one-off" re-use as a
Norwegian Ro/Ro ferry quay at Mekjarvik. In August of the same year, the UK
Government approved Shell's recommendation and by July 1999, the Mekjarvik
quay was completed. Following the controversy over the decommissioning of
Brent Spar - international governmental policies were significantly
adjusted. The legislative requirements of today have been shaped by the
debates which ensued.
In addition to Brent Spar installation the Brent Anchor Blocks and Remote
Flare structures were successfully decommissioned between 2003 and 2006 as
part of the
Brent Redundant Facilities Decommissioning Programme. In preparation
Shell conducted pre-decommissioning surveys and initiated a stakeholder
consultation process in July 2003. The structures were wholly removed to
shore for disposal/reuse in July/August 2005. Subsequent removal of any
residual debris from the seabed sites took place during summer 2006. As part
of the post-decommissioning survey the Scottish Fishermen’s Federation
conducted trawler tests in the areas, consequently issuing clean seabed
certificates confirming that any seabed debris present had been entirely
removed.
Shell is currently considering end of field life options for the remaining
infrastructure contained within the Brent field. This could mean
decommissioning of the present structures - Brent Alpha, Bravo, Charlie and
Delta platforms. A preliminary stakeholder consultation exercise has already
been initiated in January 2007. This will be followed by a series of
stakeholder dialogue sessions before the final programme is decided.
Click here for more information about how Brent Spar was decommissioned
from the Shell website.
Ekofisk
Fig: Aerial views of installations on the Ekofisk field:
a) the Ekofisk 2-4 A FTP Platform, and b) the Ekofisk Tank

In 1994, Phillips Petroleum Norway (now
ConocoPhillips Norge) initiated the
Ekofisk I Cessation project with the objective of achieving the disposal of
the field's varied range of structures in a safe, environmentally friendly
and cost-effective manner.
In October 1999, the company published an Impact Assessment Report detailing
the results of an assessment of the effects on the environment and society
estimated to result from the implementation of each of the relevant disposal
alternatives for Ekofisk I topsides, substructures, pipelines, drill
cuttings and seabed debris. A Cessation Plan was also submitted to the
Norwegian Ministry of Petroleum and Energy at that time. The proposals
concern the decommissioning of 14 steel platforms and 1 large concrete tank
(Ekofisk Tank).
The concrete tank, which weighs 1.2 million tonnes, was a candidate for
derogation under the OSPAR rules governing decommissioning. In the spring of
2001, a consultation document was sent to all the OSPAR contracting parties.
No objections were raised to the proposal to leave the concrete tank
substructure as long as it does not harm the environment in the long-term.
In June 2002, the Norwegian Parliament also approved the recommendation to
leave the tank in place.
Decommissioning of the other 14 structures and the Ekofisk Tank topsides at
Ekofisk I began in 2005/2006 and are scheduled to continue until 2013.
Heerema Marine Contractors were awarded the contract for the removal of
bridges, bridge supports and flares using heavy lift vessels. The Ekofisk
Tank topsides will be removed by AF Decom. Both companies will cooperate on
the onshore disposal part of the work, which is due to be carried out at a
new facility at Raunes in Vats, Rogaland, Norway.
Click here for
more information on the decommissioning of the Ekofisk field from the
ConocoPhillips Norge website.
Maureen
Fig: Maureen Installation being towed to shore

Oil production from the Maureen facilities became uneconomic in June 1999
following a rapid decline in production levels. There were no remaining
opportunities to increase production levels economically and Cessation of
Production (COP) was granted to the operator,
ConocoPhillips,
by the then DTI on October 7th, 1999. By that time, the plans for
decommissioning Maureen were well under way.
The Maureen platform was a unique structure since it was a steel gravity
base structure which was designed to be re-floated and moved to another
location for reuse (the Maureen owners’ preferred solution) or to a suitable
inshore location for deconstruction and recycling. The structure weighed
110,000 tonnes and was the first large structure to be decommissioned in the
world. The decommissioning programme document, which described the owners’
decommissioning recommendations, was issued for public consultation in June
2000. The UK government approved the proposals in December 2000. In June
2001 the whole platform was successfully re-floated and towed by six tugs to
a yard at Stord on the West Coast of Norway. The Maureen loading column,
which was also designed for removal, was re-floated shortly after the
platform and also towed to Stord. At 10,000 tonnes the concrete column is
the second heaviest structure to be removed after the Maureen platform.
The Maureen owners continued to seek a buyer for a possible full reuse of
the platform until the last possible moment. However, in October 2001 a
partial reuse was found for both the platform and column substructures. The
base of the platform was cut up and used as part of a deep-water quay at a
yard on Stord, while the concrete column was used as a breakwater in a
leisure marina nearby. Over 95% of the remaining parts of the structures
were reused or recycled.
Frigg
Fig: a) Concrete drilling platform 1 (CPD1) in the UK
sector of the Frigg Field, and b) Drilling Platform 2 (DP2) in the Norwegian
sector

Gas production at the Frigg Field ceased in October 2004 after 27 years of
operation. The field is unique in that it straddles the borders of both the
UK and Norwegian continental shelves and the plans for its decommissioning
had to be approved by the authorities in both countries. To simplify the
matter it was agreed that disposal of facilities on both sides of the border
would be coordinated in a single jointly agreed decommissioning programme.
Installations present on the Frigg field comprise three steel platforms and
three large concrete structures. The size and complexity posed by its
decommissioning meant that the operator
Total E&P Norge AS, on
behalf of the owners, have worked for a number of years with stakeholders to
seek the best decommissioning solution for the field. Final approval of the
Frigg Field Cessation Plan was obtained in March 2003 from the Norwegian and
UK governments. All topside facilities will be removed to shore for
disposal, as will the three steel substructures, or jackets. The three
concrete substructures, two located in the UK Sector and one in the
Norwegian Sector, will be left in place after the removal of the external
steel works. Navigation aids will be installed on each substructure. The
drill cuttings pile situated around the DP-2 platform will be left in place,
at a maximum of 20 cm thickness.
The offshore removal work is planned to last four years starting summer
2005, with the main offshore removal activities being carried out during the
calmer summer months.
Click here for more information on the decommissioning of the Frigg
field from the Total E&P Norge website.
Manifold Compression Platform (MCP-01)
Fig: Manifold Compression Platform 01 (MCP-01)

The Manifold Compression Platform MCP-01 was installed in 1976 and sits in
94m of water, 173km north-east of Aberdeen in block number 14/5 in the UK
sector. Its concrete gravity structure weighs over 386,000 tonnes. It is
operated by
Total E&P UK Limited. The original purpose of the platform was to act as
a compression and interconnection platform for the
Frigg
Transportation System (FTS) consisting of a 32” Frigg UK pipeline and a
32” Frigg Norwegian pipeline (known today as the Vesterled pipeline)
transporting gas from the Frigg reservoir to the St Fergus Gas Terminal in
Scotland.
In 1992 MCP-01 was re-configured to allow it to be operated as a
“not-normally-manned” platform controlled from the St. Fergus Gas Terminal.
Security cameras onboard monitor the platform 24 hours a day. To improve
safety and reduce maintenance, the operational equipment used on the
platform was kept to a minimum.
The two 32” pipelines entering/leaving MCP-01 continue to be in use and
therefore required rerouting to allow MCP-01 to be decommissioned. After
this process had been completed the topsides were prepared for removal, and
following statutory consultation in November 2005 permission was granted for
the early removal of the topsides structures. The timing was adjusted to
afford synchronisation with the decommissioning work also taking place on
the Frigg field, therefore achieving maximum synergy effects.
During the topsides removal process a flotel will be located next to MCP-01.
The equipment will be removed by use of a heavy lift vessel and by a “piece
small” technique where the steel is cut into smaller items for transport in
containers to shore. The offshore removal works are planned to be completed
by summer 2008. The heavy lift barge will return in the summer of 2009 to
remove temporary equipment.
Click
here for more information on the decommissioning of Manifold Compression
Platform 01 from the Total UK website.
Indefatigable
Fig: The “Juliet” (left) and “Lima” (right) platforms on
the Indefatigable field in the southern North Sea

The indefatigable gas field is situated around 75 km off the East Anglian
coast in the “Norfolk Banks” area of the southern North Sea at a depth of
around 31 m. Production came on stream in 1971. The
Shell/Esso administered section of the field is located in blocks 49/19
and 49/24 with infrastructure comprising 5 platforms (Juliet, Kilo, Mike,
Lima and November) 26 wells and 5 pipelines. The five installations were
installed between 1970 and 1988 and are small fixed steel platforms with
four six or ten legs and weighing between approximately 1,000 and 4,000
tonnes. Currently all five platforms are designated as “not normally manned”
installations. As relatively small installations none of the structures
present on the field qualify for derogations under OSPAR 98/3. After all
wells have been permanently plugged and decommissioned, and the topsides
facilities prepared and cleaned, the installations (both jackets and
topsides) will be wholly removed to shore for disposal/recycling, with a
presumption that the recycling of materials shall be maximised. It is
anticipated that the pipelines (which have a history of stable burial) will
be decommissioned in-situ, with appropriate remedial work at ends and
crossings. Due to the strong currents in this region of the southern North
Sea, together with the fact that no drilling has occurred in the area since
1992 there are no drill cuttings piles under any of he platforms. The
decommissioning recommendations formed were based upon open consultations
with the public and other interested stakeholders. Current estimates suggest
the decommissioning work will be carried out over the period 2008 to 2011.
Click here for more information from the Shell website on the
decommissioning of the Indefatigable field.
|